Attendance Summary Report

Logic ERP has corrected the WEEKLY OFFS / HOLIDAYS column of the Attendance Summary Report.


Step 1: Open the Report

  • Navigate to Payroll Reports and open the Attendance Summary Report.

  • Tick the WEEKLY OFFS / HOLIDAYS column in the report's column settings.


What's corrected

  • WEEKLY OFFS / HOLIDAYS now shows the number of days the employee worked on their own week-offs. Earlier it always showed 0. A half day worked on a week-off counts as one day.

  • Each employee's own week-offs are used: employee-wise week-offs (for example from their roster), or the week-offs of the employee's branch. Earlier every branch's week-off was applied to everyone.

  • This column will now show figures where it showed 0 before. This is intended.


Comp-off

  • Comp-off days are counted in DAYS WORKED and ABSENT DAYS, as casual leave is. A half day of comp-off counts like a half day of casual leave in DAYS WORKED, DAYS PRESENT and ABSENT DAYS, and a half day of comp-off worked on a week-off counts in WEEKLY OFFS / HOLIDAYS.