Reconciling Production WIP
How to Check That the Production Work-in-Progress Figures Agree?
In this article, we will learn how to check that the production work-in-progress (WIP) figures in Logic ERP agree with each other: the WIP value in the accounts, the WIP of each Job Order, and the quantities pending at each process. It explains where each figure comes from, a routine to follow at the end of each month, the reports to compare, and what to do when the figures do not agree.
Two Kinds of WIP
WIP value — the value of the raw material that has gone into production but has not yet come out as finished goods: raw material issued − raw material returned − value received into stock. This is the figure that goes into the accounts.
WIP quantity — the pieces pending at each process: produced in one process and not yet taken further, or issued for processing and not yet received back.
The two are not compared with each other. Where a quantity report also shows a value, it is not the raw material WIP: Branch Wise Work In Progress Analysis values pending quantities at the item rates chosen in the report, and Work In Progess - Ageing Analysis at the Job Order's cost up to that process.
Where the WIP Value Comes From
Stored WIP — used by the accounts
Logic ERP keeps a running WIP value. It is updated every time one of these entries is saved, modified or deleted:
a raw material issue against a Job Order;
a raw material return against a Job Order;
a production entry that adds the goods into stock;
a Stock Receipt - Production entry.
Each entry is added at the rate it carries:
issues and returns — the raw material rate from the costing settings (RM Rate From and RM Rate As on Update Job Order + Process Wise Net Cost) at the time the entry is saved;
goods received — the Job Order's raw material cost per piece at the time the production entry was saved.
Trading Account - Balance Sheet Groups and Balance Sheet - Balance Sheet Groups show this stored WIP when their option Include Production WIP Stock Value is ticked. The row is titled WIP Stock Value in the Trading Account (another title can be given in Production WIP Stock Value Title) and WIP Value in the Balance Sheet. It does not appear when the WIP is zero.
Job Order WIP — worked out when the report runs
Job Order Wise Work In Progress and Job Order Wise Costing From RM/Processing (column PRODUCTION WIP VALUE) work out the WIP of each Job Order from the entries every time they are run, using the same rates stored on the entries.
Keeping the WIP up to date
The rates on the entries are not changed afterwards. When a Job Order is costed again, or item, lot or costing rates are changed, both the stored WIP and the Job Order reports keep the old rates. Production WIP Reconstruction puts the current rates on the entries and rebuilds the stored WIP from them, one financial year at a time. Rates changed in one year can affect entries made in a later year, so run it for every year from the earliest one affected.
Because both figures use the same rates, they disagree only when the stored WIP has missed an entry, or when an entry is linked to a Job Order that cannot be found (see When the Figures Do Not Agree).
Month-End Routine
Run Update Job Order + Process Wise Net Cost (Production\Production Utilities), so that every Job Order has its current raw material cost per piece.
Run Production WIP Reconstruction (Production\Production Utilities) for the current financial year, and for every earlier year from the earliest one in which entries, rates or Job Order costs have changed. Take a backup first — see Production WIP Reconstruction.
Carry out Check 1 and Check 2 below. Carry out Check 3 when you also want to check the pending quantities.
Check 1: Accounts WIP Against Job Order WIP
This check compares the WIP in the accounts with the total WIP of all Job Orders.
In the accounts
Navigate to Reports/Queries\Balance Sheet and open Trading Account - Balance Sheet Groups.
Tick Include Production WIP Stock Value.
Do not tick Show Data For Current Branch Only, and do not select branches, so that all branches are included. The user running the report needs access to all branches.
Note the WIP Stock Value on the report's end date.
In the Job Order report
Navigate to Production\Production Reports/Queries\Production Raw Material Reports and open Job Order Wise Work In Progress.
Use the same end date.
Add the PRODUCTION WIP VALUE column and tick Grand Totals.
Do not select any Process, Job Order, Item or branch. This keeps the Brought Forward rows — Job Orders that still have WIP but no activity in the period — in the total.
Note the grand total of PRODUCTION WIP VALUE.
Result
After the month-end routine, the two figures are the same. A difference of a few paise can come from rounding. For anything larger, see When the Figures Do Not Agree below.
Check 2: Job Order by Job Order
This check compares the WIP of each Job Order in the two Job Order reports.
Open Job Order Wise Costing From RM/Processing (Production\Production Reports/Queries\Production Finished Goods Reports) and add the PRODUCTION WIP VALUE column.
Open Job Order Wise Work In Progress with the same end date and no branch selected.
For each Job Order, PRODUCTION WIP VALUE is the same in both reports. Both work it out up to the report's end date.
Job Order Wise Costing From RM/Processing lists Job Orders whose Job Order date falls in its period, and shows the whole Job Order, whichever branch its entries were made in. Compare it with Job Order Wise Work In Progress run for all branches.
Check 3: Pending Quantities
These three reports, under Production\Production Reports/Queries\Production Finished Goods Reports, work out the quantity pending at each process in the same way — production not yet taken further, and issues for processing not yet received back:
Stock Report - Stock Status + Production WIP Report
Work In Progess - Ageing Analysis
Branch Wise Work In Progress Analysis — read its closing columns; its other period columns show movements, not pending quantities.
Run them for the same date and the same branches, and their pending quantity for each process should agree.
Stock Report - Stock Status + Production WIP Report takes its branches from Branch Selection For Production in its configuration. Set the same branches there.
In Work In Progess - Ageing Analysis, do not use Filter On AD, which leaves out rows outside the chosen age bracket.
Set Do Not Use Next Process For Pending Entries the same way in every report you compare. Each report saves this setting in its own configuration.
Ticked — pending production is shown against the process that produced it.
Not ticked — it is shown against the next process it goes to.
Issues for processing are always shown against the process they were issued to.
With no process selected, the total pending quantity is the same either way; only the split between processes changes. With processes selected, the total for those processes can change.
Production Status Report also shows pending quantities, but it works them out differently — for example, it leaves out raw material issues to processes and filters by branch only in some report types — so it is not used for this check.
When the Figures Do Not Agree
The accounts WIP and the Job Order WIP total differ
An entry did not reach the stored WIP, or the stored WIP was not rebuilt for every year after rates were rewritten
Run Production WIP Reconstruction for every year from the earliest one affected
They still differ after Reconstruction
Raw material issued against a Job Order whose Job Order cannot be found. It counts in the accounts but under no Job Order
Ask your Logic ERP support team to check these issues
One Job Order differs between the two Job Order reports
Job Order Wise Work In Progress was run for selected branches
Run it for all branches
A Job Order is missing from Job Order Wise Costing From RM/Processing
Its Job Order date is outside the report's period
Widen the period
Pending quantities differ between the quantity reports
Different dates, branches or processes, a different Do Not Use Next Process For Pending Entries setting, or one of the report options in Check 3
Run them with the same settings
Example — a receipt missing from the accounts WIP
At the end of May, Kiran runs Trading Account - Balance Sheet Groups and sees a WIP Stock Value of ₹5,60,000. The grand total of PRODUCTION WIP VALUE in Job Order Wise Work In Progress for the same date is ₹4,00,000.
The difference, ₹1,60,000, is a Stock Receipt - Production of 400 shirts at a raw material cost of ₹400 per shirt that did not reach the stored WIP when it was saved.
No Job Order has been costed again and no rates have changed since the entries were saved. Kiran runs Production WIP Reconstruction for the year. The stored WIP is rebuilt from the entries, and Trading Account - Balance Sheet Groups now shows ₹4,00,000, the same as the Job Order report.
For how the cost of a Job Order is worked out, see Job Order Costing - Concepts.