> For the complete documentation index, see [llms.txt](https://kb.logicerp.com/llms.txt). Markdown versions of documentation pages are available by appending `.md` to page URLs; this page is available as [Markdown](https://kb.logicerp.com/logic-erp-learning-hub-tutorials-and-best-practices/production/production-reports-queries/production-raw-material-reports/job-order-wise-work-in-progress.md).

# Job Order Wise Work In Progress

## How to Read the Work-in-Progress Value of Job Orders?

In this tutorial, we will learn how to use the **Job Order Wise Work In Progress** report to see the **work-in-progress (WIP)** value of each Job Order: the raw material that has gone into production but has not yet come out as finished goods.

***

### **How WIP Is Worked Out**

For each Job Order, up to the report's end date:

**WIP = raw material issued − raw material returned − value received into stock**

* **Issued** — raw material issued to the Job Order, for example through **Raw Material Issues Against Job Order - Internal / External**, including issues linked to it through **Allocate Raw Material Issues to Job Orders** — at the cost on each issue line.
* **Returned** — returns recorded in **Consumption/Receipt of RM against JO Issues - Internal / External**.
* **Received into stock** — the quantity received × the raw material cost per piece of the Job Order. Both ways of receiving count:
  * a production entry that adds the goods into stock;
  * **Stock Receipt - Production**.
* **Opening WIP** is the same calculation for dates before the report's start date.

The raw material cost per piece is worked out by **Update Job Order + Process Wise Net Cost**, and **Production WIP Reconstruction** copies it onto the goods received. Run both, in that order, before relying on the WIP figures.

> **Example — WIP of one Job Order**
>
> Fabric worth ₹50,000 is issued to Arjun's Job Order and ₹5,000 is returned. 400 pieces are received into stock at a raw material cost of ₹100 per piece = ₹40,000.
>
> WIP = 50,000 − 5,000 − 40,000 = **₹5,000**, the raw material still in production.

***

### **Open the Report**

* Navigate to Production\Production Reports/Queries\Production Raw Material Reports and select **Job Order Wise Work In Progress**.
* Click **Configuration** and add the columns you need.

***

### **WIP Columns**

* **PRODUCTION WIP VALUE** — the closing WIP of the Job Order.
* **OPENING WIP VALUE** — the WIP at the start of the period.
* **PRODUCTION ADD IN STOCK VALUE** — the value received into stock, up to the end date.
* **RM ISSUE QUANTITY / VALUE**, **RM CONSUMED QUANTITY / VALUE** and **PENDING FOR CONSUMPTION QUANTITY / VALUE** — issued, consumed, and issued but not yet consumed.
* The WIP value is shown once for each Job Order, on its first row.
* On ordinary rows, **RM ISSUE VALUE** uses the report's own **RM Rate From** / **RM Rate As** setting, while the WIP uses the cost on each issue line. The two can therefore differ.

***

### **Report Options**

* **Hide Job Orders With No WIP Value** — shows only Job Orders whose opening or closing WIP is not zero. It works only when a WIP column is selected. The WIP totals are not changed.
* **Generate Report On Basis Of As On Date** — lists every pending issue up to the end date, with no start date, and changes the wording of the **Brought Forward** rows (see below).
* **Branch** selection — limits the report, including the WIP values, to the chosen branches.
* **Grand Totals** — adds a **Grand Totals** row.

***

### **Brought Forward Rows**

Brought Forward rows show Job Orders that still have WIP but had no activity in the report period, so that the WIP total is complete.

* They appear when the **PRODUCTION WIP VALUE** or **OPENING WIP VALUE** column is selected and no Process, Job Order or Item is selected in the report filters. They list only Job Orders that are not already in the body of the report.
* The heading reads **Brought Forward - Job Orders with WIP (no activity in this period)**.
* With **Generate Report On Basis Of As On Date** ticked, the heading reads **Brought Forward - WIP balance with no pending quantity at any process**. Each row says **Balance = RM cost not absorbed by the production receipt - job order needs re-costing.** Run **Update Job Order + Process Wise Net Cost** for these Job Orders, and then **Production WIP Reconstruction** for the year(s) in which their goods were received.
* On these rows, **RM ISSUE VALUE** is issues less returns up to the end date, and **RM ISSUE VALUE − PRODUCTION ADD IN STOCK VALUE = PRODUCTION WIP VALUE**.
* A **Brought Forward Total** row shows their opening and closing WIP; its other value columns are left blank. The Brought Forward rows are included in the grand totals.

***

### **Why WIP May Not Be Zero**

* **Material not consumed or returned** — raw material issued to a Job Order stays in WIP until it is consumed into goods received or returned.
* **Costing not up to date** — goods received before the Job Order was last costed may carry an old or zero raw material cost. Run **Update Job Order + Process Wise Net Cost** and then **Production WIP Reconstruction**.
* **Negative WIP** — the value taken out for goods received (pieces × raw material cost per piece from the last costing) is more than the material issued less returned up to the end date. Common causes:
  * the cost per piece includes material issued **after** the report's end date — this clears when the report is run to a later date;
  * the costing valued the material differently from the issue lines, for example the master rates changed or **Production WIP Reconstruction** was not run for that year — re-cost the Job Order, then run **Production WIP Reconstruction**;
  * the costing includes work-in-progress issues, or more pieces were received than the quantity the cost was divided by — check the Job Order's costing.


---

# Agent Instructions
This documentation is published with GitBook. GitBook is the documentation platform designed so that both humans and AI agents can read, navigate, and reason over technical content effectively. Learn more at gitbook.com.

## Querying This Documentation
If you need additional information that is not directly available in this page, you can query the documentation by asking a question.

Perform an HTTP GET request on the following URL with the `ask` and `goal` query parameters:

```
GET https://kb.logicerp.com/logic-erp-learning-hub-tutorials-and-best-practices/production/production-reports-queries/production-raw-material-reports/job-order-wise-work-in-progress.md?ask=<question>&goal=<user_goal>
```

`ask` is the immediate question: it should be specific, self-contained, and written in natural language.
`goal` is what the user is ultimately trying to achieve, the reason they need the answer. Sharing it helps GitBook give you a better, more relevant answer. A goal is most helpful when it describes the outcome the user wants rather than restating the question. For example, with `ask=how do I create an API token`, a goal like `automate deployments from our CI pipeline` lets GitBook tailor the answer to that use case.

The response will contain a direct answer to the question and relevant excerpts and sources from the documentation.

Use this mechanism when the answer is not explicitly present in the current page, you need clarification or additional context, or you want to retrieve related documentation sections.