Purchase Order & Delivery Note Process
YouTube: WMS – Purchase Order & Delivery Note Process?
WMS – Purchase Order & Delivery Note Process?
In this tutorial, we will understand the Procurement Process in WMS, starting from creating a Purchase Order and receiving the ordered material through a Delivery Note against Purchase Order.
This process ensures that the material received from the supplier is properly linked to the original Purchase Order and provides the foundation for the next stages of WMS, such as material verification and inward processing.
Create a Purchase Order
Navigate to the Order Processing module from the main menu.
Open the Purchase Order window.
Select the required Supplier.

Proceed to the Item Details section.
Add the items you want to order.
Enter the required quantities for each item.

Once all the required items and quantities have been entered, save the Purchase Order.
Purchase Order Purpose
The Purchase Order records the items and quantities that have been ordered from the supplier. It also serves as the reference document for receiving the material.
Create a Delivery Note Against Purchase Order
Once the Purchase Order has been placed, the next step is to receive the ordered goods.
Navigate to the Order Processing module.
Open Delivery Note Against Purchase Orders.
Select the required Supplier.
Enter the relevant document details.

Click Next to proceed to the Item Details section.
Retrieve the Purchase Order
In the Item Details section:
Tick Purchase Order. The supplier must be selected first, otherwise the message "Please Select Supplier" is shown.
Search for and select the required Purchase Order. Only the pending orders of this supplier are listed, and more than one order can be selected.

Click Refresh to retrieve the items from the selected Purchase Order, and tick the items you want to bring in.

The system will display the items that were ordered through the selected Purchase Order.
Record the Received Quantity
Now, record the quantities actually received.
Scan the Item Codes of the received products in Enter Barcode. Each scan adds to the received quantity of that item.
Continue scanning until all the received items and quantities have been entered.
Important Point
The Enter Barcode box is shown only when the Delivery Note configuration option Allow Item Scanning Only for PO is set (to Item Code, EAN Code, Set Name, Set Code or PO Lot Number). Without it, the retrieved items come in with the full pending order quantity, and you change the quantities by hand.

System Behavior
The Delivery Note records the actual physical quantity received against the items ordered through the Purchase Order.
This allows the system to maintain a clear link between the ordered quantity and the received quantity.
If the supplier delivers only part of the order, the balance stays pending on the Purchase Order and can be brought into a later Delivery Note.
Save the Delivery Note
Once all the required items and received quantities have been entered:
Review the details.
Save the Delivery Note.
Result
The Delivery Note is successfully created against the selected Purchase Order.
It records the physical receipt of the goods from the supplier and provides the basis for the next stage of the WMS procurement process.
If approval is set up for Delivery Notes, the Delivery Note must be approved before it can be retrieved in the Purchase Challan. Otherwise the message "Delivery Note:… is pending for approval. Cannot Retrieve." is shown.
WMS Procurement Flow
The procurement process covered in this tutorial can be summarized as:
Purchase Order → Delivery Note Against Purchase Orders → Purchase Challan (MRN) → Rejection/Replacement → Physical Stock Verification & Bin Transfer
In the next stages, the received material can be verified and processed further within WMS.
Final Outcome
By following this process, the business can systematically manage the procurement cycle—from placing the Purchase Order to physically receiving the material—while maintaining a proper document link between the ordered and received goods.
Last updated